The Borgsten Dolphin Project was double docked with the Byford in November 2004 for an in-service inspection.
Due to contract commitments the Byford was completed first and undocked in mid-December.
The Borgsten also had emergent work from the Structural Inspection and Maintenance Programme (SIMP) inspection and was kept in the dock until mid-March 2005. Upon completion the unit was relocated to the quay for storage and minor works before departing for a charter in June 2005.
Manhours on project – 63,944
- Services: In Service Support / Repair & Maintenance
- Client: Dolphin Drilling Limited
- Project: Borgsten Dolphin
- Date Commenced: Early November 2004
- Date Undocked: Mid March 2005
- Date Departed Quay: June 2005
The workscope included:
- Underdeck Painting
- Anchor windlasses
- Weld repairs on Anchor pockets
- Weld repairs on Chain pockets
- Weld repairs on K Nodes and columns
- Main Deck thicknesses
- Sponson structural repairs
- DG Upgrades
- Thruster upgrades
- Electrical upgrades
- Accommodation and lifesaving upgrades
- Pipework mods to HP and LP systems
Related Projects
SeaRose FPSO
- Repair & Maintenance
In January 2012, Harland & Wolff was awarded the contract for the drydocking and service of the SeaRose, a floating production, storage and offloading vessel (FPSO).
Blackford Dolphin Class Renewal Survey
- Repair & Maintenance
- Fabrication & Construction
Dolphin Drilling Limited awarded the contract for the class renewal survey dry docking of their Aker H3-type semi-submersible rig to Harland and Wolff Heavy Industries Ltd.
Pile Cluster Fabrication
- In Service Support
- Repair & Maintenance
The Borgsten Dolphin Project was double docked with the Byford in November 2004 for an in-service inspection.